Group 8 - Facility Status

This section involves the change of facility status that may affect the performance goals of a facility. The potential inability to meet performance goals may significantly affect other major and minor facilities throughout the complex. Performance goals are operating objectives necessary to accomplish an approved facility, process, or activity mission on a periodic basis. The duration of the goal may be short or long term, but should not exceed the goals of the annual operating plan.

A. Facility/Process/Activity Unscheduled Shutdown

Off-Normal

Any unscheduled shutdown of a facility, process, or activity that resulted or may result in the failure to meet approved performance goals.

B. Existing Facility/Process/Activity Shutdown Extension

Off-Normal

Any increase in an approved shutdown schedule of 1 month or greater or that resulted or may result in the failure to meet approved performance goals for an existing facility, process, or activity.

C. New Facility/Process/Activity Start-up Delay

Off-Normal

Any delay in an approved start-up schedule of 1 month or greater and which resulted or may result in the failure to meet approved performance goals for a new facility, process, or activity.